Click Stage to expand.
Construction Activities...Remove median islands on Schuylkill Avenue
Motorists...Up to three lanes northbound; One lane southbound
Pedestrians...Crosswalk on south side at Market Street; Crosswalk on north side of Chestnut Street
Bicyclists...No impacts
Construction Activities...Remove median islands...Repair deck on north side of Walnut Street intersection
Motorists...Two lanes southbound Schuylkill Avenue... Northbound Schuylkill Avenue... Periodic nighttime on I-76
Pedestrians...Crosswalk on south side at Chestnut Street... Crosswalk on north side at Walnut Street... Sidewalk on east side of Schuylkill Avenue
Bicyclists...Bike lane restrictions at Chestnut Street and Schuylkill Avenue
Construction Activities...Install ADA curb ramps at intersection of 23rd and Chestnut streets
Motorists...No impacts
Pedestrians...Crosswalks CLOSED during ramp installations
Bicyclists...Share the road east of Schuylkill Ave
Construction Activities...Install light poles
Motorists...School bus loading area may be impacted during light pole installation
Pedestrians...Sidewalk maintained during light pole installation
Bicyclists...No impacts
Construction Activities...Curb removal
Motorists...No impacts
Pedestrians...West crosswalk
Bicyclists...Minor bike lane restriction at intersection
Construction Activities...Remove and replace deck, repair steel superstructure on west side...Widen and replace sidewalk
Motorists...Two lanes northbound on Schuylkill Avenue... Southbound... Nighttime and weekend
Pedestrians...Pedestrian island and west sidewalk
Bicyclists...No impact to Bicycle Lanes except at Schuylkill Avenue/Chestnut Street intersection
*Schuylkill Avenue is built on a structure (viaduct) that covers I-76.
Construction Activities...Remove and replace deck, repair steel superstructure on east side...Widen and replace sidewalk
Motorists...Northbound Schuylkill Avenue...One lane southbound...Nighttime and weekend
Pedestrians...East sidewalk
Bicyclists...No impacts
*Schuylkill Avenue is built on a structure (viaduct) that covers I-76.
Construction Activities...Replace ramp pavement joints and drainage...Overlay ramp deck
Motorists...Ramp restricted to one lane...Nighttime and weekend
Construction Activities...Remove and replace north sidewalk...Remove north half of Span 1 and replace with lightweight fill...Rehabilitate the retaining wall along the north sidewalk...Install storm sewer
Motorists...Two lanes eastbound on Chestnut Street
Pedestrians...Sidewalk on north side of Chestnut Street...West crosswalk at 30th & Chestnut streets
Bicyclists...Use travel lane
*Chestnut Street is built on a structure between 30th and 31st streets.
Construction Activities...Remove and replace bridge deck in intersection...Repair steel superstructure
Motorists...Two lanes eastbound on Chestnut Street straddling the work area... Nighttime and weekend
Pedestrians...No impacts Bicyclists...Use travel lane
Construction Activities...Construct south sidewalk between CSX railroad and 24th Street...Install ornamental railings on Chestnut Street...Rehabilitate south wall of bridge over 24th Street...Replace south sidewalk between 23rd and 24th street...Install storm sewer
Motorists...Two lanes eastbound on Chestnut Street (right lane must turn right)...24th Street CLOSED under Chestnut Street bridge
Pedestrians...South sidewalk on Chestnut Street maintained behind barrier... 24th Street sidewalk CLOSED at bridge
Bicyclists...Use Chestnut Street travel lane... 24th Street CLOSED at Chestnut Street bridge
Construction Activities...Rehabilitate south spandrel* wall of Chestnut Street bridge over 24th Street...Replace roadway deck and sidewalks and install ornamental railing
Motorists...24th Street CLOSED under Chestnut Street
Pedestrians...Sidewalks under Chestnut Street CLOSED
Bicyclists...24th Street CLOSED under bridge...Chestnut Street bike lane ends at 24th Street
*A spandrel wall is the space between two arches or between an arch and a rectangular enclosure.
Construction Activities...Repair superstructure and substructure steel on Chestnut Street over 30th Street
Motorists...One lane in each direction
Pedestrians...One sidewalk at a time Bicyclists...No impacts
*Chestnut Street is built on a structure between 30th and 31st streets.
Construction Activities...Remove and replace deck, repair steel superstructure on west side of Schuylkill Avenue...Widen and replace sidewalk
Motorists...Two lanes northbound on Schuylkill Avenue...Southbound...Nighttime and Weekend
Pedestrians...Pedestrian island and west sidewalk on Schuylkill Avenue...North crosswalk at intersection of Schuylkill Avenue and Chestnut Street
Bicyclists...No impacts
*Schuylkill Avenue is built on a structure (viaduct) between Market and Walnut streets.
Construction Activities...Remove and replace deck, repair steel superstructure on west side of Schuylkill Avenue...Widen and replace sidewalk
Motorists...One lane southbound...Nighttime and Weekend LANE CLOSURES on I-76
Pedestrians...West sidewalk CLOSED...Pedestrian walkway is on the east side of Schuylkill Avenue
Bicyclists...No impacts
*Schuylkill Avenue is built on a structure (viaduct) between Market and Walnut streets.
Construction Activities...Replace north sidewalk...Remove and fill north half of Span 1...Rehabilitate north sidewalk retaining wall...Install storm sewer...Repair and repave Span 2 deck.
Motorists...Two lanes eastbound
Pedestrians...Sidewalk on north side CLOSED Bicyclists...Use travel lane
Construction Activities...Remove, repair steel, and replace east half of ramp deck
Motorists...One lane on ramp
No Pedestrians or Bicyclists permitted on ramp
Construction Activities...Remove middle third of roadway and bridge deck and refill arch...Continue installation of storm sewer
Motorists...Two lanes straddling work area...24th Street CLOSED at bridge
Pedestrians...No impacts on Chestnut Street...24th Street CLOSED at bridge
Bicyclists...Use travel lane on Chestnut Street...24th Street CLOSED at bridge
Construction Activities...Remove and replace deck, repair steel superstructure on west side...Widen and replace sidewalk
Motorists...Two lanes northbound...Southbound ...Nighttime and weekend
Pedestrians...Pedestrian island and west sidewalk
Bicyclists...No impacts
Construction Activities...Remove and replace deck, repair steel superstructure on west side...Widen and replace sidewalk
Motorists...One lane southbound...Nighttime and Weekend
Pedestrians...West sidewalk...Sidewalk on the east side of Schuylkill Avenue OPEN...Schuylkill Avenue/Chestnut Street intersection south sidewalk
Bicyclists...No impacts
Construction Activities...Replace south sidewalk...Remove and re-fill south half of Span 1...Repair steel superstructure...Install storm sewer....Repave south half
Motorists...Two lanes eastbound
Pedestrians...Sidewalk on south side...30th Street/Chestnut Street intersection west sidewalk...31st Street/Chestnut Street intersection east sidewalk
Bicyclists...May use sidewalk
Construction Activities...Remove pavement overlay...Repair steel superstructure and substructure...Replace west half concrete overlay
Motorists...One lane on ramp
Construction Activities...Rehabilitate bridge's north spandrel wall*, remove and replace arch fill...Construct north sidewalk between CSX railroad and 24th Street...Replace roadway deck and sidewalks and install ornamental railings...Replace north sidewalk between 24th and 23rd streets...Install storm sewer.
Motorists...Two lanes eastbound (right lane must turn right)...24th Street CLOSED at overpass
Pedestrians...Sidewalk on north side behind barrier...24th Street CLOSED at overpass
Bicyclists...Use travel lane...24th Street CLOSED at overpass
*A spandrel wall is the space between two arches or between an arch and a rectangular enclosure.
Construction Activities...Rehabilitate retaining wall supporting Schuylkill River Trail below Chestnut Street Bridge
Pedestrians...Trail under Chestnut Street bridge
Bicyclists...Trail under Chestnut Street bridge
Construction Activities...Install final pavement markings
Motorists...Short term lane closures
Pedestrians...No impacts
Bicyclists...Short term lane closures
Construction Activities...Remove and replace deck, repair steel superstructure on the east side...Widen and replace the sidewalk
Motorists...Variable two-to-three lanes northbound...Southbound
Nighttime and weekend
Pedestrians...Pedestrian island and east sidewalk
Bicyclists...No impacts
Construction Activities...Remove and replace deck, repair steel superstructure on the east side...Widen and replace the sidewalk
Motorists...Variable 0ne-or-two lanes southbound...Nighttime and weekend
Pedestrians...East sidewalk ...West sidewalk OPEN
Bicyclists...Maintain bicycle detour north on 30th Street to eastbound Market Street to southbound 23rd Street to Chestnut Street
Construction Activities...Remove and replace deck, and repair the steel superstructure of the Chestnut Street Bridge over the Schuylkill River and Schuylkill Trail...Widen and replace bridge sidewalks...Rehabilitate and strengthen the Chestnut Street arch structure over CSX railroad...Install trellis
Motorists...Chestnut Street between Schuylkill Avenue and 23rd Street OPEN
River Impacts...Schuylkill River partial closure one-half channel at a time
Pedestrians...Chestnut Street between Schuylkill Avenue an 23rd Street CLOSED...Pedestrians detour on 30th Street to Walnut Street east to 23rd Street north to Chestnut Street
Bicyclists...Chestnut Street between Schuylkill Avenue an 23rd Street OPEN
Construction Activities...Construct and remove temporary access driveway to 2400 Chestnut Street...Complete replacement of south sidewalk from 24th Street to 23rd Street
Motorists...Access to-and-from 2400 Chestnut Street Garage only
Pedestrians...Pedestrian access to and from Chestnut Street at 23rd Street only
Bicyclists...Access to and from 2400 block of Chestnut Street from 23rd Street...Chestnut Street between Schuylkill Avenue an 24th Street...
Bicycle detour: 30th Street to eastbound Market Street to southbound 23rd Street to Chestnut Street. Maintain bicycle detour north on 30th Street to eastbound Market Street to southbound 23rd Street to Chestnut Street.
Construction Activities...Pavement marking adjustments for Chestnut Street Diversion Route
Motorists...Increased traffic volume on Market Street
Pedestrians...Schuylkill Avenue to 23rd Street...
Bicyclists...Maintain bicycle detour north on 30th Street to eastbound Market Street to southbound 23rd Street to Chestnut Street.
Construction Activities...Rehabilitate retaining wall supporting Schuylkill River Trail below Chestnut Street Bridge
Pedestrians...Trail is closed under Chestnut Street bridge...
Bicyclists...Trail is closed under Chestnut Street bridge...
Construction Activities...Mill and Repave sections of Chestnut Street...Place final pavement markings
Motorists...Short term work zone restrictions
Pedestrians...None
Bicyclists...Short term work zone restrictions
Construction Activities...Construct median island...Mill, repave, and place final pavement markings
Motorists...No impacts
Pedestrians...South crosswalk at Market Street
Bicyclists...No impacts
Work Area 3: Intersection of Schuylkill Avenue and Walnut Street
Construction Activities...Construct portion of median and east sidewalk
Motorists...Northbound Walnut Street
Pedestrians...East sidewalk on Schuylkill Avenue between Walnut and Chestnut streets
Bicyclists...No impacts
Construction Activities...Rehabilitate the underside of the arch barrel spans...Mill and overlay 24th Street under Chestnut Street...Replace sidewalk and curb around bridge
Motorists...24th Street CLOSED to through traffic
Pedestrians...24th Street CLOSED at Chestnut Street bridge
Bicyclists...24th Street CLOSED at Chestnut Street bridge
Construction Activities...Restore final pavement markings
Motorists...Short term lane restrictions for pavement marking restoration
Pedestrians...No impacts Bicyclist Impacts...No impacts
Construction Activities...Construct remaining portion of east sidewalk
Motorists...One lane southbound on Schuylkill Avenue...Northbound
Pedestrians...East sidewalk...South crosswalk at Chestnut Street...North Crosswalk at Walnut Street
Bicyclists...Northbound Schuylkill Avenue
Construction Activities...Construct remaining portion of medians
Motorists...Two lanes northbound on Schuylkill Avenue...Southbound
Pedestrians...South crosswalk at Market Street
Bicyclists...Southbound Schuylkill Avenue
Construction Activities...Install ADA curb ramps
Motorists...No impacts
Pedestrians...West crosswalk
Bicyclists...No impacts